PUBLIC WORKS PROJECT UPDATES September 14, 2018 Update #19

9/15/2018

 
WISCONSIN RAPIDS PUBLIC WORKS DIVISION
PUBLIC WORKS PROJECT UPDATES
 
September 14, 2018 Update #19
 
Director of Public Works:
Joseph Terry
Phone (715)-421-8255
Email JTerry@wirapids.org
 
City Engineer:
Joe Eichsteadt Phone (715)-421-8251
Email Jeichsteadt@wirapids.org
High Street - 7th Ave N to 10th Ave N
City crews completed the majority of the topsoil restoration this week. The concrete is poured and cured and residents once again have access to their driveways. Pember has some small portions of concrete to complete then the street will be ready for asphalt.
 
Wastewater force main river crossing
Retaining wall construction began this week on Blue Heron Lane. Crews expect to finish the wall next week.
 
West Side Lift Station
Miron Construction completed the 420 cubic yards of concrete work on the outside portion of the sump well. Next week Miron plans to begin backfilling the sump well and installing the inlet pipe and manhole. The project is on-schedule for a February completion.
 
Wisconsin River Green Space and Recreation Project
This week Janke completed all of the concrete work within Demitz Park. The crew worked on placing topsoil within the park and finished installation of the new driveway into the park, which included grading the driveway and new parking lot area. They also finished concrete along 3rd Street, down to Mead Street and along 2nd Street, up to Witter Street. Lastly, riverbank stabilization was installed within the East Riverbank Conservancy and grading began for the multi-use trail. Next week Janke plans to continue working in the East Riverbank Conservancy installing riverbank stabilization and grading in preparation of the trail being poured along the river. Revi Designs will continue restoration and plantings in Demitz Park. Weather permitting; American Asphalt will be onsite to begin fine grading and paving of the driveway and parking lot in Demitz Park.
 
High Street - 12th Ave N to 17th Ave N
This week City crews completed the underground work between 14th Ave N and 15th Ave N. Next week work will continue between 13th Ave N and 14th Ave N. Residents along the 1300 block of High Street will not have direct access to their driveways during this stage of construction.
 
Van Buren Street – 8th Ave N to 10th Ave N
City crews completed the majority of the topsoil restoration this week. The concrete is poured and cured and residents once again have access to their driveways. Pember has some small portions of concrete to complete and a small portion of gas line needs to be replaced at the 7th Ave N intersection prior to asphalt paving.
 
10th & 12th St Sidewalk Project
10th St. (Grove-Wood), Wood Ave (10th-12th) and 12th St (Wood-River Run) City crews completed topsoil removals this week. Next week crews plan to shape the grade for the new walk.

Comments are closed.

    Archives

    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018

    Categories

    All
    News Release
    Office Of The Mayor
    Public Works
    Road Closure
    Wastewater

    RSS Feed

View City Directory

Contact Us :

City of Wisconsin Rapids
444 West Grand Avenue
Wisconsin Rapids, WI 54495

715-421-8200
Wisconsin Rapids App
Apple App Store
Google Play Store
city of wisconsin rapids logo
  • Government
  • Departments
  • Start/Grow Business
  • Community
  • I Want To...
  • Search